Red-pen markups back into the schematic

demi reads the schematic pages marked in red during commissioning and turns them into a change list with sheet, column and device.

Today

During commissioning, wires are moved, bridges added and parts swapped. The changes end up in red pen on the paper schematic in the cabinet or as a phone photo in an e-mail. Weeks pass before someone carries them into the electrical CAD, and some get lost on the way. Then schematic, terminal diagram and parts list no longer match the cabinet, and the customer receives documentation that does not show what was built.

An example

Elmeris commissions a control cabinet SWS-1200 for a filling line. Back come 23 pages marked in red out of 186 sheets. The agent finds 41 changes: 17 rewired conductors, 9 new bridges, 6 changed settings on motor protection breakers and one swapped frequency inverter. It reports that a new wire lands on terminal X3:22, which is already in use, and that the swapped inverter is not in the parts list. The electrical engineer takes over 39 changes in one morning and clears two with commissioning.
Fictional company, typical workflow.

Your data, wherever it lives

Red-pen changes live today as paper in the cabinet, as scans on the drive or as phone photos in e-mails. The project sits in the electrical CAD, parts list and order in the ERP. demi reads, understands and links them per cabinet, with your rights. A stack of marked pages becomes a checked change list in minutes, and your electrical engineers decide on every change.

Where the data lives today

  • Scans & paper
  • CAD & drawings
  • PDFs
  • ERP
  • E-mails
  • Folders & drives
Data LayerOne view of everything, with your rights

How demi solves it

Three layers in this order: connect the data first, then the rights, then the AI.

  1. 1 · ConnectData Layer

    Data sources in this case: scans and photos of the marked pages, the electrical CAD project with device tags, terminal and cable diagrams, plus parts list and order from the ERP. demi replaces nothing and links every markup to sheet, column and device. demi writes back only after approval.

  2. 2 · PermitPermission Layer

    The schematics of an order are visible to electrical engineering, commissioning and project management. A person in electrical engineering takes over every change; what they accept or reject is recorded with name and date in the change list.

  3. 3 · ActIntelligence Layer

    The agent recognises strokes, arrows, new wires and handwritten values and reads device tags and terminals exactly as printed. It checks every change against the project: is the terminal free, is the new part in the parts list, does a rated value change? What it cannot read with certainty it flags instead of guessing.

How it runs

  1. 1

    Commissioning scans or photographs the marked pages and sends them by e-mail.

  2. 2

    The agent assigns every markup to sheet, column and device in the electrical CAD project.

  3. 3

    It checks every change against terminal diagram, parts list and rated values and reports conflicts.

  4. 4

    Electrical engineering accepts or rejects each change and enters it in the electrical CAD.

  5. 5

    Parts list and customer documentation go out with a new revision.

What changes

  • The schematic shows the cabinet as built

  • No red-pen change gets lost any more

  • Service and spare parts work from the right parts list

What does it bring you?

Check it with your own numbers

Every starting value is an assumption you can change. The calculation sits right below, step by step.

Assumption, editable

Your numbers

Result

+346 hfreed per year

Assumptions and calculation

demi reads every red-pen change and maps it to the schematic; your electrical engineers carry it over.

8 h → 5.6 h per case

How does it run today?

What is already digital saves less: the factor lowers the share demi brings.

How we calculate

12 red-pen markup sets × 8 h × 30% × 1.0 (manual) × 12 months = 346 h

Value per year, before demi costs

Freed per year+346 h

Assumption: labour cost of €49.50 per hour in German manufacturing in 2025 (Destatis), plus workplace, IT and overheads.

= Value per year, before demi costs

+€22,490

gained per year

346 h ÷ 1,760 h per role = 0.2 full-time roles

An estimate, not a promise. The starting values are assumptions for an industrial company with 150 to 500 people.

Combine with more cases and get the package

Questions about this use case

Can demi read handwritten red-pen markups?

Yes. The agent recognises strokes, arrows, new wires and handwritten values on scans and phone photos. Uncertain spots are shown with the image cut-out so that a person decides; nothing is guessed.

Does demi write the changes straight into our electrical CAD?

No, that stays with your electrical engineers. demi supplies the checked change list with sheet, column, device and the old and new state. demi updates parts list and order in the ERP only after approval.

What happens if a change does not fit the project?

The agent reports the conflict, for example a terminal already in use, a part without a parts list line or a changed rated value that affects the cabinet's verification. It shows the spot in the schematic with the markup beside it.

Does the customer then get up-to-date documentation?

Yes. After approval demi compiles schematic, terminal diagram and parts list in the new revision into the customer documentation. Every revision shows which changes from commissioning it contains.

See this case with your data

In the demo we show you the workflow on your own systems.

Your configurator

No use cases yet

Your configurator is still empty

Add a use case from any card or case page and see what it brings per year, with the calculation. Free, no sign-up, no commitment: try it out and change any number.

Browse use cases